70-178 Practice Tests

  • 70-178 Exam with Lead2pass New Microsoft VCE and PDF Dumps-100 percent Pass Rate (61-70)

    Passing Microsoft 70-178 exam questions is guaranteed with Lead2pass. Lead2pass provides a great deal of Microsoft 70-178 preparation resources mend to step up your career with the endorsement of technical proficiency. The earlier you use Lead2pass products, the quicker you pass you 70-178 exam.

    QUESTION 61
    You enter the finish date for a task, and then assign a resource.
    You discover that the task is automatically scheduled for two weeks past the finish date you have entered.
    You need to identify the problem.
    What should you do?

    (more…)

  • Free Lead2pass 70-178 Brain Dumps is a Helpful Tool For You to Pass 70-178 Exam (41-50)

    Lead2pass provides you with the most reliable practice exams to master Microsoft 70-178 Certification. Our Microsoft questions and answers are certified by the senior lecturer and experienced technical experts in the Microsoft field. These test questions provide you with the experience of taking the actual test.

    QUESTION 41
    All tasks in your project use the Auto Schedule mode. Several tasks are in progress.
    You need to reschedule all the remaining work on the project.
    You also need to achieve this goal without having rigid constraints set to your project’s tasks. What should you do?

    (more…)

  • 70-178 Exam with Lead2pass New Microsoft VCE and PDF Dumps-100 percent Pass Rate (31-40)

    Passing Microsoft 70-178 exam questions is guaranteed with Lead2pass. Lead2pass provides a great deal of Microsoft 70-178 preparation resources mend to step up your career with the endorsement of technical proficiency. The earlier you use Lead2pass products, the quicker you pass you 70-178 exam.

    QUESTION 31
    Standard working hours are eight hours a day from Monday through Friday.
    You create a task of fixed units and set the duration to 2 days.
    You assign the task to John at 100 percent. John wants to work only 50 percent on the task.
    You change John’s assignment units to 50 percent for the task.
    Which set of values describes the specified task?

    (more…)

  • 70-178 Exam with Lead2pass New Microsoft VCE and PDF Dumps-100 percent Pass Rate (21-30)

    Lead2pass 70-178 study guides are patterned into Questions and Answers pdf format and test engine and it will sharpen your skills and expand your knowledge to obtain a definite success. Everything you need to prepare and quickly pass the 70-178 certification exams the first time ,can be found in Lead2pass study guides.

    QUESTION 21
    You need to view only the task name, start and finish dates, percentage of work completed, and a Gantt chart.
    What should you do?

    A.    Create a custom filter and a custom view.
    B.    Create a custom table and a custom group.
    C.    Create a custom filter and a custom table.
    D.    Create a custom table and a custom view.

    (more…)

  • Free Lead2pass 70-178 Brain Dumps is a Helpful Tool For You to Pass 70-178 Exam (11-20)

    Lead2pass 70-178 study guides are patterned into Questions and Answers pdf format and test engine and it will sharpen your skills and expand your knowledge to obtain a definite success. Everything you need to prepare and quickly pass the 70-178 certification exams the first time ,can be found in Lead2pass study guides.

    QUESTION 11
    Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource.
    What should you do?

    A.    Update the base project calendar.
    B.    Change the working time for the resource.
    C.    Change the maximum units for the resource.
    D.    Assign the resource only to tasks that are scheduled on the working days.

    (more…)